Review Statuses
The information below shows how the Learning Plan activity status relates to the category and grid that the Review will fall into.
Activity Status |
Planned or Finished |
Comments |
Not Scheduled |
Planned |
If there is a Review Learning Plan activity, but it has not been scheduled. No 'Task' exists. |
Scheduled |
Planned |
If there is a Review Learning Plan activity, it has been scheduled. A 'Task' is automatically created. |
In progress |
Planned |
If the Review has been started but not finished. |
Awaiting Signature |
Finished |
If the Review is finished, but pending required signatures are still to be provided. |
Completed |
Finished |
If the Review is finished and does not require any signatures. OR If the Review is finished and fully signed. |
Archived |
Finished |
If a Review type has been removed from the programme configuration. |
Not Completed |
Finished |
If a Review activity is marked as 'Not Completed'. This review status is only available for Employ-Restart delivery programmes, where the 'Completion mode' for the component is 'Tutor decides'. |
Status logic
Reviews are a different type of Learning Plan activity. For example, Review is the only Learning Plan activity that has the 'Not Scheduled' and 'Scheduled' statuses, while other have a 'Not Started' and 'In Progress' status.
These following diagrams show the flow of the status logic for:
- Review Learning Plan activity
- Review instance
- Review 'Task'
Status logic for Review Learning Plan activity
*Mark as 'Not Completed' is only applicable to Employ Restart delivery programmes.