Planning for QA

Overview

As an IQA with the Internal Verifier role, you can create a sample plan via console. The QA process consists of the following stages:

QA_process_image.png

To get started with the QA process, you must first plan for QA.

 

Planning for QA

On the learning plan, you will see some extra options that are relevant to the QA role. You can see check boxes next to each component on the left hand side. You will also see an option to show/hide where there is referred evidence.

QA__Learning_Plan_View_-_01.png

You can also see a box showing details relevant to QA planning. The box has the following information:

  • QA Required: how much QA is required for this particular learner
  • Planned for QA: how much has been planned
  • Ready for QA: what is ready for QA -  how much has been completed or how much evidence is there that has been earmarked for QA and is now ready for QA
  • Quality Assured: how much has been Quality Assured

blobid0.jpg

 

To plan a component for QA, click the options icon ⋮ on the far right. Click Plan for QA.

QA__Learning_Plan_View_-_10_-_Add_Planned.png

You can select multiple components using the checkboxes on the left.

Once you select one or more components, you will see a panel on the top. You can use Select All to select all the currently shown components. You can use the learning plan filters to narrow your list before you use the Select All option.

Once you have selected the required components, click Plan for QA.

QA__Learning_Plan_View_-_04_-_Multiple_Selected.png

After you have planned the components for QA, the system sets a flag against each of the selected learning plan components. Note the indicator against each of the three learning plan components that were planned for QA.

QA__Learning_Plan_View_-_05_-_Planned_Icon.png

Where there is something ready or available for QA, the system indicates that using the ready for QA icon on the component. In the following example - the icons indicate that two components have been planned for QA, one is ready for QA, and one has been quality assured.

QA__Learning_Plan_View_-_05.1_-_QA_Icons.png

 

Remove a component from the planned for QA list

To remove a component from the planned for QA list, click the options icon ⋮ on the far right. Click Remove from Planned for QA.

QA__Learning_Plan_View_-_09_-_Remove_Planned.png

Note that where a programme requires 100% quality assurance, the system does not allow for activities to be removed from a state of 'Planned for QA'.

 

Using filters on the Learners screen

Back on the Learners screen, you can use the Ready for QA quick filter to view the learners who have components that are ready for QA.

Tutor__01-00-Learners_list-01_QuickFilters_02.png

To carry out the QA, you must navigate to the learning plan activities that are ready for QA. For further details, see: Carrying out QA.

 

Troubleshooting

Why are some learners showing as having Unplanned QA when the programme and tutor are both set to no assessments to be verified?

This occurs when the programme was previously set to a QA percentage greater than none, and was subsequently changed back to none. The update to zero applies only to learners in the following statuses at the time of the change:

  • Active
  • Under Review
  • On Probation
  • Ready to Enrol
  • Entered EPA

Learners in any other status retain their original QA percentage and will continue to show as requiring QA verification, even after the programme setting is changed.

If learners outside these statuses are incorrectly showing Unplanned QA, their individual QA requirement will need to be updated manually. Contact Aptem Support for assistance with bulk updates.

Was this article helpful?
0 out of 0 found this helpful